Hi everyone. I'm relatively new to PA and learning on the job, so my apologies if this is a simple question that I am missing. I'm looking to create a series of events that are contingent on the date of the 1st event (which I will manually set up).

 

My organisation runs 10 and 15 week cycles and I'm looking to build a flow that creates 5 "check point events" during those cycles, however the only way I can work it out at the moment is to manually input all the dates. I feel like I'm missing something very simple. The flow would basically be: Manually set up an event -> event #2 triggered X days from event #1 -> event #3 triggered X days from event 2 etc...

 

Hope someone can help and save me some much needed time over the holiday period. 


Thanks,

1 ACCEPTED SOLUTION

Accepted Solutions
v-bofeng-msft
Community Support
Community Support

Hi @MattKinh :

Do you want to create multiple events at the same time?

  • 15 days between the start time of the second event and the first event
  • 5 days between the start time of the third event and the second event

If so ,please try this flow:

1.JPG

Reference Expression:

1\addDays(triggerBody()['date'],15)

2\addDays(triggerBody()['date_1'],15)
3\addDays(triggerBody()['date'],20)
4\addDays(triggerBody()['date_1'],20)
Best Regards,
Bof

View solution in original post

3 REPLIES 3
v-bofeng-msft
Community Support
Community Support

Hi @MattKinh :

Do you want to insert time intervals between events?

The point is to use Delay action.For example:

1.JPG

Best Regards,

Bof

 

Thanks a lot but that isn't exactly what I want. I understand that the above solution will create an event x days after the 1st event is created?

 

I am trying to create all the events at once, but automate the creation of the events so that I don't have to manually enter the start and end date for each event. So that if I make an event on Jan 1st, it automatically makes 2nd event on jan 15th, 3rd event on jan 20th.... but if I make the first event on jan 5th it makes second event on Jan 20th and 3rd on Jan 25th.

v-bofeng-msft
Community Support
Community Support

Hi @MattKinh :

Do you want to create multiple events at the same time?

  • 15 days between the start time of the second event and the first event
  • 5 days between the start time of the third event and the second event

If so ,please try this flow:

1.JPG

Reference Expression:

1\addDays(triggerBody()['date'],15)

2\addDays(triggerBody()['date_1'],15)
3\addDays(triggerBody()['date'],20)
4\addDays(triggerBody()['date_1'],20)
Best Regards,
Bof

View solution in original post

Helpful resources

Announcements
MPA_User Group Leader_768x460.jpg

Manage your user group events

Check out the News & Announcements to learn more.

V3_PVA CAmpaign Carousel.png

Community Challenge - Giveaways!

Participate in the Power Virtual Agents Community Challenge

Carousel 2021 Release Wave 2 Plan 768x460.jpg

2021 Release Wave 2 Plan

Power Platform release plan for the 2021 release wave 2 describes all new features releasing from October 2021 through March 2022.

R2 (Green) 768 x 460px.png

Microsoft Dynamics 365 & Power Platform User Professionals

DynamicsCon is a FREE, 4 half-day virtual learning experience for 11,000+ Microsoft Business Application users and professionals.

Top Solution Authors
Users online (1,960)