Create A Task based on date

Hi Everyone,

 

I am new to Microsoft flows and forms. I am trying to create a Task in the planner based on the  deadline of submission of the project( is filed in forms)

 

When the user fills the forms I have one variable which asks for when the deadline of the project.

based on the deadline date   I Have to create A task in the planner which should be completed before 10 days actual deadline date 

 

but  I am not able create a task when the user not having 10 days deadline ( which means the user feed information in form and his project complete in 5 days) How slove this problem?  

1 ACCEPTED SOLUTION

Accepted Solutions
edgonzales
Most Valuable Professional
Most Valuable Professional

@Anonymous Ok, I think I've got it sorted out.  Here's what I heard:

  • If the difference between the Project Due Date and today is 7 or more, the Task Due Date will be 2 days less.

  • If the difference is 2-6 days out, then it will be 1 day less.

  • Any sooner, and the Task Due Date will be the same as the Project Due Date.

I've made a flow chart here:20190620a.PNG

There's a bunch going on here (for the beginner) and my usual caveat is that there are probably more elegant ways to do this, but these are the tools I know how to use.

  1. The first thing we want to do is get everything in the same timezone.  Since all of the backend math is going to be in UTC, we want to convert the due date from the form to that.  (I used a manual trigger since it seemed like the trigger part of your Flow was working fine.  You'll want to change the Source Time Zone in the second box to your local timezone.
    20190620b.PNG

  2. We want to set up variables to hold the dates in a special format called "ticks".  This is what Flow (and a lot of other things, apparently) use to do math with dates.  Here, I've initialized a variable for today, the due date, and the difference (all Integer), and then one we'll use as the Task Due Date (string).
    20190620c.PNG

  3. For the UTC value, I used an expression that counts the number of 'ticks' for right now, and then divided that by the number of ticks in a day:  "DIV(ticks(utcNow()),864000000000)" (without the quotes).  For the Due Date ticks, I used "DIV(ticks(body('Convert_Due_Date_to_UTC')) ,864000000000)" where 'Convert_Due_Date_to_UTC' is the dynamic output of Step 1.
  4. To get the difference between the two (DateDiff), I used "sub(variables('varTicksDue'),variables('varUTCNowTicks'))" which subtracts one variable from another.
  5. Finally, I set the default of TaskDueDate to the converted Project Due Date.  That may change later depending on the math.
  6. Next, we want to adjust the TaskDueDate based on what the DateDiff is, right?  We do this with conditions.  There are other ways to do this, but I nested the conditions because I wanted different results based on the input.  Conditions let you ask a question, and then choose a path if the answer is "Yes" and a different path if the answer is "No".  The first question I asked was if the DateDiff was 7 days or more.
  7. If the answer was yes, I want to remove two days from the Project Due Date and make that my TaskDueDate.  You can do this with the "Subtract from Time" action and then the "Set Variable" action:
    20190620d.PNG

     

  8. If the answer is "No" (meaning the Project due date is less than 7 days out), then I want to ask another question to see if it is within 2 days.  That means your "No" path will have another condition inside it like this:
    20190620g.PNG

     

  9. If the answer to "Is it less than two days out" is Yes, we want the TaskDueDate to stay as the default (Project Due Date), so the "Yes" path can actually stay blank.  On the "No" path, we want to use the same method as Step 7 to remove one day and update the TaskDueDate variable.
  10. Last, we get to create the task.  But before we do that, we want to format the date/time to what Planner is expecting.  I use Convert Timezone for this, but there are other ways.  Not the upper/lower casing on the format...that does matter.
    20190620e.PNG

     

    And then the create task:20190620f.PNG

I hope that helps.  I did a more thorough write up here, but I think this one covers your scenario.  Keep us posted.

 

Thanks!

-Ed-

 

 

 

If this reply has answered your question or resolved your challenge, please consider marking it as a Solution. This helps other users find it more easily via search.

 

View solution in original post

9 REPLIES 9
edgonzales
Most Valuable Professional
Most Valuable Professional

@Anonymous 

Hi there!  So, this one was fun since I haven't ever used these functions before and they were behaving....'oddly'.  You can totally do this with an expression, but I don't know the exact syntax and I thought this was more fun.

 

In between getting your date (in the form) and adding the task in Planner, add two steps:

 

First is "Subtract from Time" - This one is pretty self-explanatory in the steps, but I had no idea it existed:20190618a.PNG

That step will back up 10 days and generate a date, but it also includes the time, which messes things up on the Create Task Step.  Again, you can do all of this with an expression, but this is the hammer I have:20190618b.PNG

Note the Format String.  The case of the letters does matter, and I thought it was weird that I had to switch like that...but it worked.  Essentially, we're taking the input date/time, keeping the same timezone, and spitting out the same time in a new format that only includes the date.  Feel free to adjust the Destination TimeZone, but I think Planner might do that already for you.20190618c.PNG

On the Create Task site, you can grab everything else from the Form and just add the "Converted Time" as your Due Date.  Should work splendidly.  

 

Keep us posted, though.

-Ed-

 

 

If this reply has answered your question or resolved your challenge, please consider marking it as a Solution. This helps other users find it more easily via search.

Anonymous
Not applicable

@edgonzales  I have created a task if there no 10 days gap for the deadline, for example, a student fill form today and his deadline after 3 days, in this case, I getting error message task is not create how to solve this problem if student has not have 10 days gap for deadline 

edgonzales
Most Valuable Professional
Most Valuable Professional

Ah, that makes sense.  We'd have to set a condition to check for that.  What would your (Pre-Flow) process be when this happens?

 

-Ed-

Anonymous
Not applicable

@edgonzales  I Would like to set the pre-flow process both to create a task.

 

Condition 1: if it has 10  days map create a task with the given date.

 

Condition 2: if it does not have 10  days also create a task-based deadline before on the same deadline day with or 2 days before the deadline.  

edgonzales
Most Valuable Professional
Most Valuable Professional

ok, and just poking the box a bit:  What if the deadline is inside that one day? 

What I meant with the "Pre-Flow" part was what did this process look like before you started automating?  Like xRM solutions, Flow is a great way to automate existing processes and when we're building brand new processes (in Flow, or out), it's a good idea to sketch out the steps and consider what to do when something falls "outside of the machine".

 

I'll start building something now using some conditions and we'll see how that looks.

Anonymous
Not applicable

if the deadline is inside that one day means to create the task and have a task deadline on the same day.

Anonymous
Not applicable

@edgonzales if the deadline is inside that one day means to create the task and have a task deadline on the same day.

v-lin-msft
Post Prodigy
Post Prodigy

Hi @Anonymous,

 

I feel confused that why cannot create a task have no 10 days gap for deadline.

You said that I getting error message task is not create how to solve this problem if student has not have 10 days gap for deadline. Could you share us the wrong message?

This is my flow configuration that get detail from the MS Form, then get the detail and create a task in my plan, you can refer to it:

Annotation 2019-06-21 143105.png

Annotation 2019-06-21 143047.png

 

 

 

You said that when a student submits a task with a deadline of more than ten days, I guess your purpose should be to send an email to remind the student to complete the task ten days before the deadline. However, if the completion date of student submission is within ten days, there is no way to send the reminder email of ten days ago. Then you can set a reminder email of two days or one day ago. This is another flow I built based on my guess of your purpose:

 

Step1: Create an action Recurrence, the flow will trigger every day, then get the list of tasks.

Annotation 2019-06-21 144319.png

Step2: Add a condition that if Due Date time is equal to 10 days or 2 days or 1 day later:

If yes, send remind email.

(Please convert the format of UtcNow() date).

Annotation 2019-06-21 144707.png

I hope it can help you. If you still have questions, please contact us.

 

Best Regards,

Community Support Team _ Lin Tu

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

 

edgonzales
Most Valuable Professional
Most Valuable Professional

@Anonymous Ok, I think I've got it sorted out.  Here's what I heard:

  • If the difference between the Project Due Date and today is 7 or more, the Task Due Date will be 2 days less.

  • If the difference is 2-6 days out, then it will be 1 day less.

  • Any sooner, and the Task Due Date will be the same as the Project Due Date.

I've made a flow chart here:20190620a.PNG

There's a bunch going on here (for the beginner) and my usual caveat is that there are probably more elegant ways to do this, but these are the tools I know how to use.

  1. The first thing we want to do is get everything in the same timezone.  Since all of the backend math is going to be in UTC, we want to convert the due date from the form to that.  (I used a manual trigger since it seemed like the trigger part of your Flow was working fine.  You'll want to change the Source Time Zone in the second box to your local timezone.
    20190620b.PNG

  2. We want to set up variables to hold the dates in a special format called "ticks".  This is what Flow (and a lot of other things, apparently) use to do math with dates.  Here, I've initialized a variable for today, the due date, and the difference (all Integer), and then one we'll use as the Task Due Date (string).
    20190620c.PNG

  3. For the UTC value, I used an expression that counts the number of 'ticks' for right now, and then divided that by the number of ticks in a day:  "DIV(ticks(utcNow()),864000000000)" (without the quotes).  For the Due Date ticks, I used "DIV(ticks(body('Convert_Due_Date_to_UTC')) ,864000000000)" where 'Convert_Due_Date_to_UTC' is the dynamic output of Step 1.
  4. To get the difference between the two (DateDiff), I used "sub(variables('varTicksDue'),variables('varUTCNowTicks'))" which subtracts one variable from another.
  5. Finally, I set the default of TaskDueDate to the converted Project Due Date.  That may change later depending on the math.
  6. Next, we want to adjust the TaskDueDate based on what the DateDiff is, right?  We do this with conditions.  There are other ways to do this, but I nested the conditions because I wanted different results based on the input.  Conditions let you ask a question, and then choose a path if the answer is "Yes" and a different path if the answer is "No".  The first question I asked was if the DateDiff was 7 days or more.
  7. If the answer was yes, I want to remove two days from the Project Due Date and make that my TaskDueDate.  You can do this with the "Subtract from Time" action and then the "Set Variable" action:
    20190620d.PNG

     

  8. If the answer is "No" (meaning the Project due date is less than 7 days out), then I want to ask another question to see if it is within 2 days.  That means your "No" path will have another condition inside it like this:
    20190620g.PNG

     

  9. If the answer to "Is it less than two days out" is Yes, we want the TaskDueDate to stay as the default (Project Due Date), so the "Yes" path can actually stay blank.  On the "No" path, we want to use the same method as Step 7 to remove one day and update the TaskDueDate variable.
  10. Last, we get to create the task.  But before we do that, we want to format the date/time to what Planner is expecting.  I use Convert Timezone for this, but there are other ways.  Not the upper/lower casing on the format...that does matter.
    20190620e.PNG

     

    And then the create task:20190620f.PNG

I hope that helps.  I did a more thorough write up here, but I think this one covers your scenario.  Keep us posted.

 

Thanks!

-Ed-

 

 

 

If this reply has answered your question or resolved your challenge, please consider marking it as a Solution. This helps other users find it more easily via search.

 

Helpful resources

Announcements

Exclusive LIVE Community Event: Power Apps Copilot Coffee Chat with Copilot Studio Product Team

It's time for the SECOND Power Apps Copilot Coffee Chat featuring the Copilot Studio product team, which will be held LIVE on April 3, 2024 at 9:30 AM Pacific Daylight Time (PDT).     This is an incredible opportunity to connect with members of the Copilot Studio product team and ask them anything about Copilot Studio. We'll share our special guests with you shortly--but we want to encourage to mark your calendars now because you will not want to miss the conversation.   This live event will give you the unique opportunity to learn more about Copilot Studio plans, where we’ll focus, and get insight into upcoming features. We’re looking forward to hearing from the community, so bring your questions!   TO GET ACCESS TO THIS EXCLUSIVE AMA: Kudo this post to reserve your spot! Reserve your spot now by kudoing this post.  Reservations will be prioritized on when your kudo for the post comes through, so don't wait! Click that "kudo button" today.   Invitations will be sent on April 2nd.Users posting Kudos after April 2nd at 9AM PDT may not receive an invitation but will be able to view the session online after conclusion of the event. Give your "kudo" today and mark your calendars for April 3, 2024 at 9:30 AM PDT and join us for an engaging and informative session!

Tuesday Tip: Unlocking Community Achievements and Earning Badges

TUESDAY TIPS are our way of communicating helpful things we've learned or shared that have helped members of the Community. Whether you're just getting started or you're a seasoned pro, Tuesday Tips will help you know where to go, what to look for, and navigate your way through the ever-growing--and ever-changing--world of the Power Platform Community! We cover basics about the Community, provide a few "insider tips" to make your experience even better, and share best practices gleaned from our most active community members and Super Users.   With so many new Community members joining us each week, we'll also review a few of our "best practices" so you know just "how" the Community works, so make sure to watch the News & Announcements each week for the latest and greatest Tuesday Tips!     THIS WEEK'S TIP: Unlocking Achievements and Earning BadgesAcross the Communities, you'll see badges on users profile that recognize and reward their engagement and contributions. These badges each signify a different achievement--and all of those achievements are available to any Community member! If you're a seasoned pro or just getting started, you too can earn badges for the great work you do. Check out some details on Community badges below--and find out more in the detailed link at the end of the article!       A Diverse Range of Badges to Collect The badges you can earn in the Community cover a wide array of activities, including: Kudos Received: Acknowledges the number of times a user’s post has been appreciated with a “Kudo.”Kudos Given: Highlights the user’s generosity in recognizing others’ contributions.Topics Created: Tracks the number of discussions initiated by a user.Solutions Provided: Celebrates the instances where a user’s response is marked as the correct solution.Reply: Counts the number of times a user has engaged with community discussions.Blog Contributor: Honors those who contribute valuable content and are invited to write for the community blog.       A Community Evolving Together Badges are not only a great way to recognize outstanding contributions of our amazing Community members--they are also a way to continue fostering a collaborative and supportive environment. As you continue to share your knowledge and assist each other these badges serve as a visual representation of your valuable contributions.   Find out more about badges in these Community Support pages in each Community: All About Community Badges - Power Apps CommunityAll About Community Badges - Power Automate CommunityAll About Community Badges - Copilot Studio CommunityAll About Community Badges - Power Pages Community

Tuesday Tips: Powering Up Your Community Profile

TUESDAY TIPS are our way of communicating helpful things we've learned or shared that have helped members of the Community. Whether you're just getting started or you're a seasoned pro, Tuesday Tips will help you know where to go, what to look for, and navigate your way through the ever-growing--and ever-changing--world of the Power Platform Community! We cover basics about the Community, provide a few "insider tips" to make your experience even better, and share best practices gleaned from our most active community members and Super Users.   With so many new Community members joining us each week, we'll also review a few of our "best practices" so you know just "how" the Community works, so make sure to watch the News & Announcements each week for the latest and greatest Tuesday Tips!   This Week's Tip: Power Up Your Profile!  🚀 It's where every Community member gets their start, and it's essential that you keep it updated! Your Community User Profile is how you're able to get messages, post solutions, ask questions--and as you rank up, it's where your badges will appear and how you'll be known when you start blogging in the Community Blog. Your Community User Profile is how the Community knows you--so it's essential that it works the way you need it to! From changing your username to updating contact information, this Knowledge Base Article is your best resource for powering up your profile.     Password Puzzles? No Problem! Find out how to sync your Azure AD password with your community account, ensuring a seamless sign-in. No separate passwords to remember! Job Jumps & Email Swaps Changed jobs? Got a new email? Fear not! You'll find out how to link your shiny new email to your existing community account, keeping your contributions and connections intact. Username Uncertainties Unraveled Picking the perfect username is crucial--and sometimes the original choice you signed up with doesn't fit as well as you may have thought. There's a quick way to request an update here--but remember, your username is your community identity, so choose wisely. "Need Admin Approval" Warning Window? If you see this error message while using the community, don't worry. A simple process will help you get where you need to go. If you still need assistance, find out how to contact your Community Support team. Whatever you're looking for, when it comes to your profile, the Community Account Support Knowledge Base article is your treasure trove of tips as you navigate the nuances of your Community Profile. It’s the ultimate resource for keeping your digital identity in tip-top shape while engaging with the Power Platform Community. So, dive in and power up your profile today!  💪🚀   Community Account Support | Power Apps Community Account Support | Power AutomateCommunity Account Support | Copilot Studio  Community Account Support | Power Pages

Super User of the Month | Chris Piasecki

In our 2nd installment of this new ongoing feature in the Community, we're thrilled to announce that Chris Piasecki is our Super User of the Month for March 2024. If you've been in the Community for a while, we're sure you've seen a comment or marked one of Chris' helpful tips as a solution--he's been a Super User for SEVEN consecutive seasons!   Since authoring his first reply in April 2020 to his most recent achievement organizing the Canadian Power Platform Summit this month, Chris has helped countless Community members with his insights and expertise. In addition to being a Super User, Chris is also a User Group leader, Microsoft MVP, and a featured speaker at the Microsoft Power Platform Conference. His contributions to the new SUIT program, along with his joyous personality and willingness to jump in and help so many members has made Chris a fixture in the Power Platform Community.   When Chris isn't authoring solutions or organizing events, he's actively leading Piasecki Consulting, specializing in solution architecture, integration, DevOps, and more--helping clients discover how to strategize and implement Microsoft's technology platforms. We are grateful for Chris' insightful help in the Community and look forward to even more amazing milestones as he continues to assist so many with his great tips, solutions--always with a smile and a great sense of humor.You can find Chris in the Community and on LinkedIn. Thanks for being such a SUPER user, Chris! 💪 🌠  

Tuesday Tips: Community Ranks and YOU

TUESDAY TIPS are our way of communicating helpful things we've learned or shared that have helped members of the Community. Whether you're just getting started or you're a seasoned pro, Tuesday Tips will help you know where to go, what to look for, and navigate your way through the ever-growing--and ever-changing--world of the Power Platform Community! We cover basics about the Community, provide a few "insider tips" to make your experience even better, and share best practices gleaned from our most active community members and Super Users.   With so many new Community members joining us each week, we'll also review a few of our "best practices" so you know just "how" the Community works, so make sure to watch the News & Announcements each week for the latest and greatest Tuesday Tips!This Week: Community Ranks--Moving from "Member" to "Community Champion"   Have you ever wondered how your fellow community members ascend the ranks within our community? What sets apart an Advocate from a Helper, or a Solution Sage from a Community Champion? In today’s #TuesdayTip, we’re unveiling the secrets and sharing tips to help YOU elevate your ranking—and why it matters to our vibrant communities. Community ranks serve as a window into a member’s role and activity. They celebrate your accomplishments and reveal whether someone has been actively contributing and assisting others. For instance, a Super User is someone who has been exceptionally helpful and engaged. Some ranks even come with special permissions, especially those related to community management. As you actively participate—whether by creating new topics, providing solutions, or earning kudos—your rank can climb. Each time you achieve a new rank, you’ll receive an email notification. Look out for the icon and rank name displayed next to your username—it’s a badge of honor! Fun fact: Your Community Engagement Team keeps an eye on these ranks, recognizing the most passionate and active community members. So shine brightly with valuable content, and you might just earn well-deserved recognition! Where can you see someone’s rank? When viewing a post, you’ll find a member’s rank to the left of their name.Click on a username to explore their profile, where their rank is prominently displayed. What about the ranks themselves? New members start as New Members, progressing to Regular Visitors, and then Frequent Visitors.Beyond that, we have a categorized system: Kudo Ranks: Earned through kudos (teal icons).Post Ranks: Based on your posts (purple icons).Solution Ranks: Reflecting your solutions (green icons).Combo Ranks: These orange icons combine kudos, solutions, and posts. The top ranks have unique names, making your journey even more exciting! So dive in, collect those kudos, share solutions, and let’s see how high you can rank!  🌟 🚀   Check out the Using the Community boards in each of the communities for more helpful information!  Power Apps, Power Automate, Copilot Studio & Power Pages

Find Out What Makes Super Users So Super

We know many of you visit the Power Platform Communities to ask questions and receive answers. But do you know that many of our best answers and solutions come from Community members who are super active, helping anyone who needs a little help getting unstuck with Business Applications products? We call these dedicated Community members Super Users because they are the real heroes in the Community, willing to jump in whenever they can to help! Maybe you've encountered them yourself and they've solved some of your biggest questions. Have you ever wondered, "Why?"We interviewed several of our Super Users to understand what drives them to help in the Community--and discover the difference it has made in their lives as well! Take a look in our gallery today: What Motivates a Super User? - Power Platform Community (microsoft.com)

Users online (4,545)