Do Until loop is not working as expected

Hello,

 

We have developed a flow for approval process(Sequential), We are facing issues with Power Automate-

  1. Do until : Flow is not waiting for the approval task response, it is completing the flow though we have used “Start and wait for an approval” action inside “Do until” loop.
  2. There is a limit of 30 days maximum a flow instance can run, so is there any solution to this because there are chances that the approval can stay idle for more than 30 days? Please suggest if any.

Thanks in advance for the clarification.

 

Best regards,

Amar

1 REPLY 1
PrasadAthalye
Super User
Super User

Refer Long Running Flow solution from @RezaDorrani .

 

What is the timeout on do until? Is the action timing out? If you are using Start and Wait for an approval, it should wait unless action times out.

 

You will have to capture timeout by using run after actions and restart the flow again. Design it in such a way that you bring the flow back to same state where it timed out.

Please Like and Mark this as Answer if it resolves your Issue.

Power Automate Community

Helpful resources

Announcements
Community Connections 768x460.jpg

Community & How To Videos

Check out the new Power Platform Community Connections gallery!

User Group Leader Meeting January 768x460.png

Calling all User Group Leaders!

Don't miss the User Group Leader meetings on January, 24th & 25th, 2022.

Top Solution Authors
Top Kudoed Authors
Users online (1,484)