cancel
Showing results for 
Search instead for 
Did you mean: 
Reply
bruno-dr
Frequent Visitor

Flow run only once

Hi everyone,
 
I am facing a trouble with my flow.
 
The trigger to verify each time that an task is completed does work only once. I need to run this part of flow every time that a task is finish.
 
Dou you have an ideia about the solution?
 
Best Regards 
 
Bruno
 
https://www.dropbox.com/s/885m0e4q2642b47/Flow.png?dl=0
1 ACCEPTED SOLUTION

Accepted Solutions
v-bacao-msft
Community Support
Community Support

 

Hi @bruno-dr ,

 

It is recommended that you could create two Flows to achieve your needs.

One is used to create a new task, and the other is used to monitor whether the specified task has been completed.

 

Here you need to add a TaskId field in the List to record the task id in order to update the list item.

Delete When a task is completed and the following configuration and save Flow, then create another Flow as follows.

Use TaskId to determine if there is a specified item in the list, and if so, update the item.

Image reference:

28.PNG29.PNG

Please take a try.

 

Best Regards,

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

4 REPLIES 4
yashag2255
Dual Super User II
Dual Super User II

Hi @bruno-dr 

 

Can you please post a screenshot of the entire flow here? The screenshot that you have shared has some parts cut off. I wanted to check the trigger that you are using and some consecutive actions too. 

 

Also it would be helpful if you could transalte to english (the actions on the flow)

 

Hope this Helps!

 

If this reply has answered your question or solved your issue, please mark this question as answered. Answered questions helps users in the future who may have the same issue or question quickly find a resolution via search. If you liked my response, please consider giving it a thumbs up. THANKS!

@yashag2255, thanks for your reply.

I have translated and shared a full picture and a packet (to import) if you want. I appreciate a lot your thoughts.

Flow picture: https://www.dropbox.com/s/e0c78ypr9idbahv/Flow.docx?dl=0

Flow Packet:https://www.dropbox.com/s/6voj5csafh8fw3s/abap_20190823133049.zip?dl=0

If you need to some information, please send me a message, so I can reply quickly.

Best Regards.
Bruno
v-bacao-msft
Community Support
Community Support

 

Hi @bruno-dr ,

 

It is recommended that you could create two Flows to achieve your needs.

One is used to create a new task, and the other is used to monitor whether the specified task has been completed.

 

Here you need to add a TaskId field in the List to record the task id in order to update the list item.

Delete When a task is completed and the following configuration and save Flow, then create another Flow as follows.

Use TaskId to determine if there is a specified item in the list, and if so, update the item.

Image reference:

28.PNG29.PNG

Please take a try.

 

Best Regards,

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

@v-bacao-msft  Many thanks for your reply.

I created tho flows to control the stages and worked fine.

 

Thanks!

 

Bruno

Helpful resources

Announcements
Process Advisor

Introducing Process Advisor

Check out the new Process Advisor community forum board!

MPA User Group

Welcome to the User Group Public Preview

Check out new user group experience and if you are a leader please create your group

V3_PVA CAmpaign Carousel.png

Community Challenge - Giveaways!

Participate in the Power Virtual Agents Community Challenge

Carousel 2021 Release Wave 2 Plan 768x460.jpg

2021 Release Wave 2 Plan

Power Platform release plan for the 2021 release wave 2 describes all new features releasing from October 2021 through March 2022.

Users online (2,302)