Get Wunderlist Task when a Sharepoint list is Modificated

Hello,

 

In other flow, I create a Wunderlist Task, and save the Id of this Wunderlist Task in a Sharepoint list.

 

In this flow, when the Sharepoint Item is modified I want to recover the Id of the Wunderlist Task to get the information from the Wunderlis task.

 

However I can't see the field from the Sharepoint list in the dynamic content, I only have access to the Sharepoint ID item.

 

How can I recover the fields from the Sharepoint Item?

 Captura.PNG

 

Thank you.

1 ACCEPTED SOLUTION

Accepted Solutions
Sebas
Level: Powered On

Re: Get Wunderlist Task when a Sharepoint list is Modificated

Hello Mabel,

 

Thanks for your help, I will test your solution.

 

Anyway I want to tell you how I solved the problem, it is not nice but it is work. What I did was to create a step "Create a Task" in Wunderlist, because only for this step, you can see in the dynamic content all the fields, so I added the field to the "Create a Task", and I copied this field and pasted in "Get Task" in Wunderlist, and this worked.

 

Anyway I will test your solution.

 

Thanks

 

 

2 REPLIES 2
Community Support Team
Community Support Team

Re: Get Wunderlist Task when a Sharepoint list is Modificated

Hi Sebas,

 

I guess that you should have created a column in SharePoint list for Wunderlist Task ID. If yes, to get the Task ID, please try to add Compose action in your flow.

 

Please try if the following configuration would work for you.

4.PNG

 

Best regards,
Mabel Mao

Community Support Team _ Mabel Mao
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Sebas
Level: Powered On

Re: Get Wunderlist Task when a Sharepoint list is Modificated

Hello Mabel,

 

Thanks for your help, I will test your solution.

 

Anyway I want to tell you how I solved the problem, it is not nice but it is work. What I did was to create a step "Create a Task" in Wunderlist, because only for this step, you can see in the dynamic content all the fields, so I added the field to the "Create a Task", and I copied this field and pasted in "Get Task" in Wunderlist, and this worked.

 

Anyway I will test your solution.

 

Thanks

 

 

Helpful resources

Announcements
firstImage

Microsoft Business Applications Virtual Launch Event

Join us for an in-depth look at the new innovations across Dynamics 365 and the Microsoft Power Platform.

firstImage

Watch Sessions On Demand!

Continue your learning in our online communities.

Power Platform 2019 Release Wave 2 Plan

Power Platform 2019 Release Wave 2 Plan

Features releasing from October 2019 through March 2020

thirdimage

Flow Community User Group Member Badge

Fill out a quick form to claim your user group badge now!

fifthimage

Microsoft Learn

Learn how to build the business apps that you need

sixthImage

Power Platform World Tour

Find out where you can attend!

seventhimage

Webinars & Video Gallery

Watch & learn from the Flow Community Video Gallery!

Top Kudoed Authors
Users Online
Currently online: 47 members 4,489 guests
Please welcome our newest community members: