FrankWoody
New Member

Help with Planner + Power Automate +excel

I have a planner with several tasks, and the problem I'm having is that people are changing the project's end date without communicating, so they extend the deadline and it's like there's no previous deadline.

So my idea would be to export the planner once a week with all its information so that I have mainly the project end date saved and then process this data to check if there is any change in the project deadline.

I wanted to configure Automate to export planner information and fill an excel sheet with the date of export, and every week I would do that but filling excel as a database. It is possible ?

1 REPLY 1
tom_riha
Super User
Super User

Hello @FrankWoody ,

it is possible, but you'd still have to compare the dates between the two Excel exports to see if they changed. A better solution could be to build a solution similar to the one described here to get notified on regular basis if there was some change.



[ If I have answered your question, please Accept the post as a solution. ]
[ If you like my response, please give it a Thumbs Up. ]

[ I also blog about Power Automate solutions even for non-IT people. ]

Helpful resources

Announcements
Microsoft 365 Conference – December 6-8, 2022

Microsoft 365 Conference – December 6-8, 2022

Join us in Las Vegas to experience community, incredible learning opportunities, and connections that will help grow skills, know-how, and more.

Difinity Conference 2022

Difinity Conference 2022

Register today for two amazing days of learning, featuring intensive learning sessions across multiple tracks, led by engaging and dynamic experts.

European SharePoint Conference

European SharePoint Conference

The European SharePoint Conference returns live and in-person November 28-December 1 with 4 Microsoft Keynotes, 9 Tutorials, and 120 Sessions.

Users online (5,434)