How to add certian time to date with flow

Hi there,

I am trying to maky flow, where I after filling a form I will make an item in the list with dates which were given in form and I will add certain time to these dates. It is my work arounf to make events in SharePoint calendar which will have all vacations.

 

I have problem with time zones I guess, because right now my flow is almost correct, as long as in log I have corect Outputs, but unfortunately data are not correct in the list.

 

This is my Output:

 

output.png

 

And this is data in SharePoint list:

 

data-list.png

 

Here is my flow:

flow.pngflow1.png

 

 

I am not sure, where I have mistake... I checked SharePoint timezone and it is UTC+1...

 

Thank you for help.

Kirill

1 ACCEPTED SOLUTION

Accepted Solutions
Community Support
Community Support

Hi @Kirill-PRG ,

 

Do you mean you want to cut back 2 hours in the sharepoint list date which is created from the form?

 

If yes, you could refer to my steps below to cut back 2 hours:

1.png

 

The expression for the Od column should as below and please replace the Convert time zone with yours:

addHours(body('Convert_time_zone'),-2)

The expression for the Do column should as belowand please replace the Convert time zone with yours:

addMinutes(addHours(body('Convert_time_zone'),21),59)

 

Please let me know if your problem could be solved.

 

Best regards,

Alice       

 

Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

2 REPLIES 2
Community Support
Community Support

Hi @Kirill-PRG ,

 

Do you mean you want to cut back 2 hours in the sharepoint list date which is created from the form?

 

If yes, you could refer to my steps below to cut back 2 hours:

1.png

 

The expression for the Od column should as below and please replace the Convert time zone with yours:

addHours(body('Convert_time_zone'),-2)

The expression for the Do column should as belowand please replace the Convert time zone with yours:

addMinutes(addHours(body('Convert_time_zone'),21),59)

 

Please let me know if your problem could be solved.

 

Best regards,

Alice       

 

Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

Hi @v-alzhan-msft ,

 

Thank you for your help. It works! Thank you to introducing me expressions in flow, never used them, but now I can see it is very useful 🙂

 

Have a nice day!

Helpful resources

Announcements
Microsoft Ignite

Microsoft Ignite

Join digitally, March 2–4, 2021 to explore new tech that's ready to implement. Experience the keynote in mixed reality through AltspaceVR!

New Super Users

Meet the Power Automate Super Users!

Many congratulations to the Season 1 2021 Flownaut Crew!

New Badges

New Solution Badges!

Check out our new profile badges recognizing authored solutions!

MPA Community Blog

Power Automate Community Blog

Check out the community blog page where you can find valuable learning material from community and product team members!

Users online (38,287)