I'm currently looping the tasks contained in my plans. I want to apply logic based on the task's Progress (ie. Not Started, In Progress or Completed). However, I'm not finding the Progress option in the Dynamic content?

 

progress question.jpg

1 REPLY 1
Expiscornovus
Dual Super User
Dual Super User

Hi @DanFou,

 

If you want to check the in Progress tasks you can use the percentcomplete property. Tasks which are in progress are set to 50%.

Btw, not started are 0% and completed 100%.

 

valuepercentcomplete50.png

Helpful resources

Announcements
Power Platform Conf 2022 768x460.jpg

Join us for Microsoft Power Platform Conference

The first Microsoft-sponsored Power Platform Conference is coming in September. 100+ speakers, 150+ sessions, and what's new and next for Power Platform.

May UG Leader Call Carousel 768x460.png

June User Group Leader Call

Join us on June 28 for our monthly User Group leader call!

MPA Virtual Workshop Carousel 768x460.png

Register for a Free Workshop

Learn to digitize and optimize business processes and connect all your applications to share data in real time.

Power Automate Designer Feedback_carousel.jpg

Help make Flow Design easier

Are you new to designing flows? What is your biggest struggle with Power Automate Designer? Help us make it more user friendly!

Top Solution Authors
Top Kudoed Authors
Users online (1,436)