Hi,

I have created an approval flow which i have shared with my staff for leave request. The flow is triggered from a button where the user enters there dates for leave, it request approval, sends an email and adds an out of office to there emails. 

 

It all works but the final action setup automatic replies fails every time with the following error:-

 

{
"status": 400,
"message": "The scheduled duration for sending automatic replies isn't valid.\r\nclientRequestId: 0ac7f645-59d5-4d46-8984-808034b6ba42\r\nserviceRequestId: c490a3cb-4805-4b59-82e9-62863a535cd1",
"source": "office365-uks.logic-ase-uksouth.p.azurewebsites.net"
}
 
If i use the flow it works perfect. Can anyone see what is wrong?
 
Regards,
Chris
 
Capture.PNG
1 ACCEPTED SOLUTION

Accepted Solutions
Highlighted
Super User III
Super User III

Re: Manager Approval For Leave

@Barber_Chris 

It appears as though the SetUp automatic replies action does not want the start and end time to be the same.  To work around this issue, you can add a time component to the end time - the start time will default to the beginning of the day.  See my screen shot below.  I added a comment with the expression that I used.  I used the addMinutes expression and selected the End Date from Dynamic properties.  I add 1439 minutes to the start date - this is one minute less than 24 hours.

AutoReply.jpg

 

If I have answered your question, please mark your post as Solved.
If you like my response, please give it a Thumbs Up.

Scott

View solution in original post

6 REPLIES 6
Highlighted
Super User III
Super User III

Re: Manager Approval For Leave

@Barber_Chris 

Can you post a screen shot from design view of the configuration of the action that failed (the last action)?

 

If I have answered your question, please mark your post as Solved.
If you like my response, please give it a Thumbs Up.

Scott
Highlighted
Helper III
Helper III

Re: Manager Approval For Leave

Capture.PNGInkedCapture1_LI.jpg

Highlighted
Super User III
Super User III

Re: Manager Approval For Leave

@Barber_Chris :

Can you post a screen shot of the Set-up Automatic replies action in design view so that I can see how you have it configured rather than from the run history.  The error is suggesting that there is an issue with how you have that action configured.

 

 

If I have answered your question, please mark your post as Solved.
If you like my response, please give it a Thumbs Up.

Scott
Highlighted
Helper III
Helper III

Re: Manager Approval For Leave

Hi Scott,Capture.PNGCapture1.PNGCapture2_LI.jpgSee below. 

 

 

 

Highlighted
Super User III
Super User III

Re: Manager Approval For Leave

@Barber_Chris 

It appears as though the SetUp automatic replies action does not want the start and end time to be the same.  To work around this issue, you can add a time component to the end time - the start time will default to the beginning of the day.  See my screen shot below.  I added a comment with the expression that I used.  I used the addMinutes expression and selected the End Date from Dynamic properties.  I add 1439 minutes to the start date - this is one minute less than 24 hours.

AutoReply.jpg

 

If I have answered your question, please mark your post as Solved.
If you like my response, please give it a Thumbs Up.

Scott

View solution in original post

Highlighted
Helper III
Helper III

Re: Manager Approval For Leave

Thanks Scott, your a start, that worked a treat!!!


Helpful resources

Announcements
Community Conference

Power Platform Community Conference

Find your favorite faces from the community presenting at the Power Platform Community Conference!

FirstImage

Microsoft Ignite 2020

Check out the announcement of Power Platform content at Microsoft Ignite!

thirdImage

Experience what's new for Power Automate

Join us for an in-depth look at the new Power Automate features and capabilities at the free Microsoft Business Applications Launch Event.

firstImage

Power Platform 2020 release wave 2 plan

Features releasing from October 2020 through March 2021

Top Solution Authors
Top Kudoed Authors
Users online (6,556)