Hi MS Flow Community,

 

Our team has issues with MS Planner which is from an admin level.

 

I wanted to write a workaround flow to help keep track of our Planner task but it seems the column or property for the Assignee does not work.

 

I get this error blow;

{
  "error": {
    "code": "",
    "message": "Schema validation has failed. Validation for field 'Assignments', on entity 'Task' has failed: The assignee id is invalid.",
    "innerError": {
      "request-id": "fd34f8fa-60cf-4528-97c7-650498222018",
      "date": "2018-10-05T12:09:39"
    }
  }
}

Here is a summary of what i tried to create

MS Teams & Planner Flow.JPG

Does anyone know why the 'Assignee' property does not work??

1 ACCEPTED SOLUTION

Accepted Solutions
Community Support Team
Community Support Team

Re: Planner Assignee Property does not work

Hi @Tosyn_88,

 

Is the column type of AssignedTo in your SharePoint List Person/Group?

If so, then the Assigned User id should be filled in the Create a task action using AssignedTo Email.

I did a test on my side, it work, as below:

34.PNG

35.PNG

 

Best Regards,

Barry

 

 

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
11 REPLIES 11
Community Support Team
Community Support Team

Re: Planner Assignee Property does not work

Hi @Tosyn_88,

 

I'm afraid I didn't fully understand the intent of the Flow you created.

Could you provide more details and explanations?

Could you provide a full screenshot of your current configured Flow?

I am curious why you use Get items action instead of Get item after When an item is created.

Could you provide the details of the SharePoint list?

I want to know which output in the SharePoint list is to be populated in the Planner task and the Teams message.

In addition, the error message mentions The assignee id is invalid, please ensure that the content filled into the Assigned User Id is in accordance with the requirements of the Field (The id or email address of the user to assign this task to).

 

Best Regards,

Barry

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Tosyn_88
Level: Powered On

Re: Planner Assignee Property does not work

Hi @v-bacao-msft

 

Thank you for the follow up, appreciate it Smiley Happy

 

The details of the flow is as follows;

MS Teams & Planner Flow1.JPGMS Teams & Planner Flow2.JPG

 

The SharePoint list is as follows;

MS Teams & Planner Flow3.JPGThe [AssignedTo] can be any variable of members within my team so i cannot assign a direct email as the data varies from task to task.

Community Support Team
Community Support Team

Re: Planner Assignee Property does not work

Hi @Tosyn_88,

 

Is the column type of AssignedTo in your SharePoint List Person/Group?

If so, then the Assigned User id should be filled in the Create a task action using AssignedTo Email.

I did a test on my side, it work, as below:

34.PNG

35.PNG

 

Best Regards,

Barry

 

 

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Administrator
Administrator

Re: Planner Assignee Property does not work

Hello, @Tosyn_88!

Thank you for posting on the Flow Community Forum! Have you had an opportunity to apply @v-bacao-msft‘s recommendation to adapt your Flow? If yes, and you find that solution to be satisfactory, please go ahead and click “Accept as Solution” so that this thread will be marked for other users to easily identify!

Thank you for being an active member of the Flow Community!

-Gabriel
Flow Community Manager

-Gabriel
Microsoft Flow Community Manager
Tosyn_88
Level: Powered On

Re: Planner Assignee Property does not work

@v-bacao-msftand @GabrielStJohn

 

Thank you both for the swift responses, really appreciate the help.

 

I have tried the solution provided and it failed.  I had yet to offer a response due to me not checking all facets of why it failed due to more urgent work commitments.

 

It seems the issue is around the [user] information from the exchange. The last error i remmeber was "404: Not found" but as i said, i still want to check properly.

 

I will ensure to check the flow again this week and provide a detailed feedback.

 

Thanks, you guys are awesome!

Highlighted
Tosyn_88
Level: Powered On

Re: Planner Assignee Property does not work

Hi @v-bacao-msft

 

I have tried the steps you advised and the flow failed Smiley Sad 

 

Here is the resultMS Teams & Planner Flow4.JPG

 

It seems the issue is around the email section. It does not translate from the sharepoint list to planner.

 

Is there no object to identify a user profile or user email on planner??

 

Output error;

 

 

Body
{
  "error": {
    "code": "",
    "message": "Referenced User or Group (my work email) is not found.",
    "innerError": {
      "request-id": "fe3406a4-91c0-44a7-a1a3-b2e93aa23e99",
      "date": "2018-10-16T13:01:44"
    }
  }
}

Thank you for all the help, super glad with how quick your responses are Smiley Very Happy

 

Community Support Team
Community Support Team

Re: Planner Assignee Property does not work

Hi @Tosyn_88,

 

The error message says "Referenced User or Group (my work email) is not found.", I think it should be that the email address populated here is not a member of the organization.

Please ensure that the Email of AssignedTo saved in the SharePoint list belongs to your organization so that it can be searched correctly.

Take a try and see if issue still exists.

 

Best Regards,

Barry

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Administrator
Administrator

Re: Planner Assignee Property does not work

Hello, @Tosyn_88!

Thank you for posting on the Flow Community Forum! Have you had an opportunity to apply @v-bacao-msft‘s recommendation to adapt your Flow? If yes, and you find that solution to be satisfactory, please go ahead and click “Accept as Solution” so that this thread will be marked for other users to easily identify!

Thank you for being an active member of the Flow Community!

-Gabriel
Flow Community Manager

-Gabriel
Microsoft Flow Community Manager
Tosyn_88
Level: Powered On

Re: Planner Assignee Property does not work

@v-bacao-msft

 

Thank's for the follow up. 

 

This particular flow came about as a work-around for another flow which i had originally tried to create.

 

It seems our issue at the moment is searching the correct exchange database.

 

So the original Flow was for to post to MS Teams whenever a new task is created with the details of the task and who it is assigned to by adding prefix of "@"

 

It failed as seen below which was due to the fact that there is no object to identify the variable of the user profile the task is assigned to (I had tried writing one).

 

MS Teams & Planner Flow5.JPG

 

MS Teams & Planner Flow6.JPG

This is the error response;

 

Unable to process template language expressions in action 'Post_message' inputs at line '1' and column '2563': 'The template language expression 'triggerBody()['assignedTo']['user']['displayName']' cannot be evaluated because property 'assignedTo' doesn't exist, available properties are '@odata.etag, planId, bucketId, title, orderHint, assigneePriority, percentComplete, startDateTime, createdDateTime, dueDateTime, hasDescription, previewType, completedDateTime, completedBy, referenceCount, checklistItemCount, activeChecklistItemCount, conversationThreadId, id, createdBy, appliedCategories, assignments'. Please see https://aka.ms/logicexpressions for usage details.'.

After this failed, i then decided to perhaps use a SharePoint list in hopes it would be able to pick out the user variable as well but that also doesnt work Smiley Sad 

Meloenewoen
Level: Power Up

Re: Planner Assignee Property does not work

Hi

 

I have the same problem. However, I'm not sure if it is a Flow bug or a Planner bug because when I'm using planner and I assign a task to someone by typing the name, I have to manually select the user to assign the task. Pressing "enter" does not work. Maybe that is the reason we can't assign tasks to someone starting from a flow. 

 

This is a really blocking issue. Could you please provide a solution for us?

RodolfoMCP
Level: Power Up

Re: Planner Assignee Property does not work

Hello,

 

Did we get any resolution on this?

 

I tried a basic flow, but is giving me issues with the Assignee value.

 

Outlook task assigned to Y user >Create a Task on Planner on X Bucket> Assign to "assigned to" field from Outlook task. Error.

 

If I remove the assigne value, it runs perfectly.

Helpful resources

Announcements
firstImage

Microsoft Business Applications Virtual Launch Event

Join us for an in-depth look at the new innovations across Dynamics 365 and the Microsoft Power Platform.

firstImage

Watch Sessions On Demand!

Continue your learning in our online communities.

Power Platform 2019 Release Wave 2 Plan

Power Platform 2019 Release Wave 2 Plan

Features releasing from October 2019 through March 2020

thirdimage

Flow Community User Group Member Badge

Fill out a quick form to claim your user group badge now!

fifthimage

Microsoft Learn

Learn how to build the business apps that you need

sixthImage

Power Platform World Tour

Find out where you can attend!

seventhimage

Webinars & Video Gallery

Watch & learn from the Flow Community Video Gallery!

Top Kudoed Authors
Users Online
Currently online: 50 members 4,725 guests
Please welcome our newest community members: