Planner to Power BI via Flow

Hello,

 

I am currently trying to get some information about projects from Planner into Power BI. As there sadly is no direct connection I wanted to use Flow.

 

I currently use the following flow:

PlannerFlow.JPG

 

Problem here is, that it does not only insert newly added tasks to the dataset but everyone every time a new task is created. Is there a workaround for this? Maybe using an Excel list to compare the listed tasks and filtering them before inserting them into Power BI?

 

Thanks for help 🙂

 

2 ACCEPTED SOLUTIONS

Accepted Solutions
Super User
Super User

Re: Planner to Power BI via Flow

Hello @maxze,

 

So if you want to add task to PowerBI from Planner, use as second action Get a task.

Planner.jpg

P.

View solution in original post

Community Support Team
Community Support Team

Re: Planner to Power BI via Flow

Hi @maxze,

 

I agree with @vecerpa's suggestions and methods. If you want to add information about the newly created task to Power BI Dataset, you only need to get the contents of this one task.

You could configure Add rows to a dataset directly using the Dynamic content of the trigger output, or configure the Get a task action according to @vecerpa method first.

In addition, if you want to add information about the task assigned to yourself to the Dataset, you could use "When a task is assigned to me" as the trigger.

Please take a try.

 

Best Regards,

Barry

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

6 REPLIES 6
Super User
Super User

Re: Planner to Power BI via Flow

Hi @maxze,

 

First of all I would like to understand what are you trying to achieve?

You are trigerring Flow when new task is added to Planner and then you are listing all tasks within this Planner and creating new items in PowerBI.

So this means that each time there is new task whole list of tasks that are in Planner is added to PowerBI.

P.

 

maxze
Level: Powered On

Re: Planner to Power BI via Flow

Hi,

 

I want to integrate an status overview of tasks like the one available in the "Charts"-section, but in a Power BI report. I thought I could use data like Date created, Date finished, Date due and Date started to determine whether a task has not been started, is in progress, is leate or is completed.

 

What you describe is my problem. I would like to have Flow add the one new project to the dataset when it is created.

Super User
Super User

Re: Planner to Power BI via Flow

Hello @maxze,

 

So if you want to add task to PowerBI from Planner, use as second action Get a task.

Planner.jpg

P.

View solution in original post

Community Support Team
Community Support Team

Re: Planner to Power BI via Flow

Hi @maxze,

 

I agree with @vecerpa's suggestions and methods. If you want to add information about the newly created task to Power BI Dataset, you only need to get the contents of this one task.

You could configure Add rows to a dataset directly using the Dynamic content of the trigger output, or configure the Get a task action according to @vecerpa method first.

In addition, if you want to add information about the task assigned to yourself to the Dataset, you could use "When a task is assigned to me" as the trigger.

Please take a try.

 

Best Regards,

Barry

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

maxze
Level: Powered On

Re: Planner to Power BI via Flow

Thank you very much to both of you! A shame I did not think of that myself.

 

Now there just needs to be an action to update rows in the dataset, when a task in Planner is changed.

 

Regards

Inspired1
Level: Powered On

Re: Planner to Power BI via Flow

Hello @maxze ,

did you get this ready? I'm also doing integration between Planner and Power Bi. My problem is that, I can't get the priority or labels to my excel table which I have connected to Power BI. 

 

Do you have a solution for how to get the priority or labels from planner with flow?

 

Helpful resources

Announcements
thirdimage

Power Automate Community User Group Member Badge

Fill out a quick form to claim your user group badge now!

firstImage

Incoming: New and improved badges!

We've given our badges an overhaul and also added some brand new ones!

fifthimage

Microsoft Learn

Learn how to build the business apps that you need.

sixthImage

Power Platform World Tour

Find out where you can attend!

seventhimage

Webinars & Video Gallery

Watch & learn from the Power Automate Community Video Gallery!

Top Kudoed Authors (Last 30 Days)
Users online (5,001)