Hi,

 

I have a flow which will trigger when an item is created in a list, it will create an item (fill in due date) in a task list.

I have a condition, when task status is equal to completed, the flow should send an email, if not equal, do nothing.

The user has a certain amount of time to complete his task (before the due date), if he completes his task, the user should manually marked his task as completed.

 

But now the problem is that flow always considers the task as not completed, even if the user has marked his task as completed before the due date. Is there a solution for something like this?

 

Task 1.PNGTask 2.PNG

 

 

1 ACCEPTED SOLUTION

Accepted Solutions
Community Support Team
Community Support Team

Re: Task marked as completed, in flow marked as not completed

Hi @Gines,

 

Could you please share a bit more about your Task list?

Further, could you please show a bit more about the Task Status column? Is it a Choice type column in  your SharePoint list?

 

I assume that the Task Status column is a Choice type column within your SharePoint list, I have create a Task list on my side and the data structure of it as below:15.JPG

Note: TaskName is a Single line of text type column, Executor is a Person or group type column, Due Date is a Date and Time type column and Task Status type column is a Choice type column. The screenshot of Task Status column as below:16.JPG

The Default value of Task Status column is Incompleted.

 

  • I have made a test on my side and please take a try with the following workaround:
  • Add a "When an item is created" trigger.
  • Add a "Compose" action, rename it as "AddDays", Inputs set to following formula:
  • addDays(triggerBody()?['Created'],1)
    Add a "Create item" action, specify Site Address and List Name, Due Date field set to output of "Compose" (AddDays) action.
  • Add a "Delay" action, Count set to 2 and Unit set to Minute. I use "Delay" action instead of "Delay Until" action for test.
  • Add a "Get item" action, specify Site Address and List Name, Id field set to ID dynamic content of "Create item" action.
  • Add a Condition, left input box set to Task Status Value dynamic content of above "Get item" action, right input box set to Completed. Within middle drop down, choose is equal to. 
  • Within "If/yes" branch of Condition, add a "Send an email" action.

Image reference:17.JPG

 

18.JPG

Note: On my side, I add a "Delay" action within my flow for test, on your side, you could change it into "Delay Until" action. The configuration as below:20.JPG

 

 

The flow works successfully as below:19.JPG

 

Best regards,

Kris

 

 

 

Community Support Team _ Kris Dai
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

2 REPLIES 2
Community Support Team
Community Support Team

Re: Task marked as completed, in flow marked as not completed

Hi @Gines,

 

Could you please share a bit more about your Task list?

Further, could you please show a bit more about the Task Status column? Is it a Choice type column in  your SharePoint list?

 

I assume that the Task Status column is a Choice type column within your SharePoint list, I have create a Task list on my side and the data structure of it as below:15.JPG

Note: TaskName is a Single line of text type column, Executor is a Person or group type column, Due Date is a Date and Time type column and Task Status type column is a Choice type column. The screenshot of Task Status column as below:16.JPG

The Default value of Task Status column is Incompleted.

 

  • I have made a test on my side and please take a try with the following workaround:
  • Add a "When an item is created" trigger.
  • Add a "Compose" action, rename it as "AddDays", Inputs set to following formula:
  • addDays(triggerBody()?['Created'],1)
    Add a "Create item" action, specify Site Address and List Name, Due Date field set to output of "Compose" (AddDays) action.
  • Add a "Delay" action, Count set to 2 and Unit set to Minute. I use "Delay" action instead of "Delay Until" action for test.
  • Add a "Get item" action, specify Site Address and List Name, Id field set to ID dynamic content of "Create item" action.
  • Add a Condition, left input box set to Task Status Value dynamic content of above "Get item" action, right input box set to Completed. Within middle drop down, choose is equal to. 
  • Within "If/yes" branch of Condition, add a "Send an email" action.

Image reference:17.JPG

 

18.JPG

Note: On my side, I add a "Delay" action within my flow for test, on your side, you could change it into "Delay Until" action. The configuration as below:20.JPG

 

 

The flow works successfully as below:19.JPG

 

Best regards,

Kris

 

 

 

Community Support Team _ Kris Dai
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

Gines
Level: Powered On

Re: Task marked as completed, in flow marked as not completed

Hi Kris,

 

Thank you very much for your help, it worked. I had to use the 'Get item' action so the flow will know that an item is modified to a new value.

 

For your information, I used the standard task list from SharePoint (not a custom list) and the Task Status column is a standard column in the task list (with values as completed, in progress, deferred,...).

Helpful resources

Announcements
thirdimage

Power Automate Community User Group Member Badge

Fill out a quick form to claim your user group badge now!

firstImage

Incoming: New and improved badges!

We've given our badges an overhaul and also added some brand new ones!

fifthimage

Microsoft Learn

Learn how to build the business apps that you need.

sixthImage

Power Platform World Tour

Find out where you can attend!

seventhimage

Webinars & Video Gallery

Watch & learn from the Power Automate Community Video Gallery!

Top Kudoed Authors (Last 30 Days)
Users online (5,166)