Update Planner Tasks from Excel

Hi,

 

I'm trying to create a flow to update planner task from Excel. I have an action to list rows from table then an action to Update Planner Task within an Apply to action. The problem is the "Update Planner Task" is looking for Task ID's as opposed to task name. Hoping someone can suggest some way to retrieve task IDs, match these to Task name then update the corresponding task?

 

Thanks

 
 

Capture.JPG

1 ACCEPTED SOLUTION

Accepted Solutions
Highlighted
Community Support
Community Support

Re: Update Planner Tasks from Excel

 

Hi @pmc101 ,

 

The recommendation here is to add a field to the table to store the task id. Even if the task id can be used to filter the task id, some problems will occur. Because we cannot guarantee that each task name is unique, if there are two duplicate task names, it will cause some errors.

 

Best Regards,

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

2 REPLIES 2
Highlighted
Community Support
Community Support

Re: Update Planner Tasks from Excel

 

Hi @pmc101 ,

 

The recommendation here is to add a field to the table to store the task id. Even if the task id can be used to filter the task id, some problems will occur. Because we cannot guarantee that each task name is unique, if there are two duplicate task names, it will cause some errors.

 

Best Regards,

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

Highlighted
Frequent Visitor

Re: Update Planner Tasks from Excel

Hi v-bacoa,

 

Thanks for your response. I had hoped there was a more dynamic way to achieve this although I appreciate the challenge that duplicate task names would create so users would need police this.

 

For now, as per your suggestion I added a TaskID field to the plan update worksheet. I exported the plan to Excel from Planner and used vlookup to add the Task IDs to the spreadsheet then the flow worked fine.

 

Thanks again.

Paul

Helpful resources

Announcements
Community Conference

Power Platform Community Conference

Check out the on demand sessions that are available now!

Power Platform ISV Studio

Power Platform ISV Studio

ISV Studio is designed to become the go-to Power Platform destination for ISV’s to monitor & manage published applications.

Upcoming Events

Experience what’s next for Power Automate

See the latest Power Automate innovations, updates, and demos from the Microsoft Business Applications Launch Event.

Top Solution Authors
Top Kudoed Authors
Users online (6,923)