Hello everyone,
I'm facing an unusual problem with my flow to update a planner task from excel values.
It seems that "Update a task" is correctly identifying my task based on a title value/reference number, however the output always gives me 404 "The requested item is not found", halting the flow.
The whole flow looks like this:
I'm just trying to update the dates on the planner.
Any help will be greatly appreciated.
Sincerely,
Em
Solved! Go to Solution.
Hi @Emellar ,
Please replace the value Title configured in the Task Id field with value Id.
Best Regards,
Hi @Emellar ,
Please replace the value Title configured in the Task Id field with value Id.
Best Regards,
Wow, thank you so much. I thought I tried everything... I spent far too much time on this and the solution is so simple.
Appreciate the help.
Dive into the Power Platform stack with hands-on sessions and labs, virtually delivered to you by experts and community leaders.
Watch Nick Doelman's session from the 2020 Power Platform Community Conference on demand!
User | Count |
---|---|
40 | |
36 | |
35 | |
34 | |
27 |
User | Count |
---|---|
39 | |
38 | |
33 | |
31 | |
25 |