i ha ve a flow which adds either 1,3 or 12 months to a date field but i am getting inconsitant behaviour does anyone have any ideas?

adding one month gives a month and a dayadding one month gives a month and a dayadding three months is giving 2 days less than 3 monthsadding three months is giving 2 days less than 3 monthsadding 12 months gives exactly 12 monthsadding 12 months gives exactly 12 months

2 REPLIES 2
Community Support
Community Support

Hi @garywalker,

 

I did a test on my side and I also met the situation you mentioned.

The span of adding a month here should be without considering that this month may have 30/31/28/29 days.

I did the another test, and when I alternate between the leap year and the peace year, there will be a day when I add 12 months.

36.PNG

So I suggest changing the Time unit to Day will be more precise.

 

Best Regards,

Barry

Community Support Team _ Barry
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Thanks for looking in to this for me.

Unfortunately, we really need it to be adding months as day/weeks would not meet our acceptance criteria. Where would be the best place to raise this as a bug?

Helpful resources

Announcements
Community Conference

Power Platform Community Conference

Check out the on demand sessions that are available now!

MPA Community Blog

Power Automate Community Blog

Check out the community blog page where you can find valuable learning material from community and product team members!

Top Solution Authors
Top Kudoed Authors
Users online (9,057)