send email when a project online task is completed to the next assigned resource

Is there a way in Microsoft Project Online to trigger an email notification based on a tasks predecessor being completed to say that the task is ready to go?

2 REPLIES 2
v-bofeng-msft
Community Support
Community Support

Hi @MarioIb2b ,

 

Please try:

vbofengmsft_0-1653024669237.jpeg

 

 

Best Regards,

Bof

Hi @v-bofeng-msft thanks for your answer. 

does this work for project web? I see you use planner. I think the way is with dataverse.

Helpful resources

Announcements
Power Platform Conf 2022 768x460.jpg

Join us for Microsoft Power Platform Conference

The first Microsoft-sponsored Power Platform Conference is coming in September. 100+ speakers, 150+ sessions, and what's new and next for Power Platform.

MPA Virtual Workshop Carousel 768x460.png

Register for a Free Workshop

Learn to digitize and optimize business processes and connect all your applications to share data in real time.

Power Automate Designer Feedback_carousel.jpg

Help make Flow Design easier

Are you new to designing flows? What is your biggest struggle with Power Automate Designer? Help us make it more user friendly!

Top Solution Authors
Users online (2,721)