Creating Planner Tasks from Excel - error date format

Hi,

i created a flow that creates a planner tasks from a list of rows in excel.

when using UTCNOW and ADDDAYS as parameters it woked fine, but when im trying to get the date as input form the excekl im getting an eror.

below some screenshots to assist:

1. the excel date:

image.png

2. flow - create a task

image.png

3. error message

"The request is invalid:\r\nCannot convert the literal '43662' to the expected type 'Edm.DateTimeOffset'.",
"innerError": {
"request-id": "1fa2c77f-93f7-493d-b9c6-c6f833f52add",
"date": "2019-06-26T15:27:17"
 
thanks a lot
Perez
1 ACCEPTED SOLUTION

Accepted Solutions
Perez
Helper V
Helper V

 i found another workaround that work for me, i put as a start date UTCNOW and in my excel im giving numeric intervals per task from day 1.

 

thanks a lot for your repsonses

View solution in original post

9 REPLIES 9

Hi @Perez 

 

This is an issue with the excel connector and the date type data format on the excel column. I would suggest you to first convert the datatype of your excel column to type text and then run this flow (use the fomrat date time function to format the string to date and time)

 

Hope this Helps!

If this reply has answered your question or solved your issue, please mark this question as answered. Answered questions helps users in the future who may have the same issue or question quickly find a resolution via search. If you liked my response, please consider giving it a thumbs up. THANKS!

Hi @yashag2255 ,

thanks for your fast reply.

i tried to implement, it didnt worked, i think i didnt got the formatDateTimefunction correctly.

i tried: formatDateTime(item()['Due Date'],'dd/MM/yyyy')

is this correct? if not can you help with putting the correct expression

 

the error i got:

InvalidTemplate. Unable to process template language expressions in action 'Create_a_task' inputs at line '1' and column '1980': 'In function 'formatDateTime', the value provided for date time string '43662' was not valid. The datetime string must match ISO 8601 format.'.

 

thanks,

Perez

Hi @Perez 

 

The expression is correct but the date format that you are getting from Excel is not. Were you able to change the column data type to text in excel?

Hi @Perez ,

 

It is a known issue that Date and time returned from the Excel Online table will be converted to a string but not a date.

 

You need to use a function to format it to a valid date and time.

 

Please check the following flow for a reference.

 

Compose is used to get the actual return value of the Start date.

 

In Compose2, input the following code to get the exact date:

addDays('1899-12-30',int(outputs('Compose')),'yyyy-MM-dd')

1.PNG2.PNG

 

Best regards,

Mabel

 

Community Support Team _ Mabel Mao
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Perez
Helper V
Helper V

 i found another workaround that work for me, i put as a start date UTCNOW and in my excel im giving numeric intervals per task from day 1.

 

thanks a lot for your repsonses

marco_popolizio
Regular Visitor

Hello,

I have exactly the same problem described above and until now I've understood I have to use the expression

addDays('1900-01-01',int(items('_')?['Date'])) ...

However I have only very basic knowledge of Flow and can't figure out how to make the expression work...

Can anyone tell me exactly what to do? 😞

 

Cattura.PNG

Hi I've got this same issue. I was able to add in your expressions with the Compose 1 and Compose 2 to get the right date.  However I'm stuck as to what to do after that?  How do you get the correct date in the "Create a Task" operation?  I inserted your Compose operations just above my already existing "Create a Task" operations and still got the same error.  Thanks,

@Miel  the solution as proposed by msftis working fine, you should use the formulas as described in his response, than just use the second compose output as your new date value

auteur17
Regular Visitor

@Perez 

Hello!

On the above thread, I am successful at doing the date conversion, but like @Miel I am not able to find where the output is after the date has been converted.

 

Can you assist in assigning the date value to another field later in the flow?

 

Thank you in advance!

-- Matt

Helpful resources

Announcements
Power Platform Conf 2022 768x460.jpg

Join us for Microsoft Power Platform Conference

The first Microsoft-sponsored Power Platform Conference is coming in September. 100+ speakers, 150+ sessions, and what's new and next for Power Platform.

New Ideas Forum MPA.jpg

A new place to submit your Ideas for Power Automate

Announcing a new way to share your feedback with the Power Automate Team.

MPA Virtual Workshop Carousel 768x460.png

Register for a Free Workshop

Learn to digitize and optimize business processes and connect all your applications to share data in real time.

MPA Licensing.jpg

Ask your licensing questions at the Power Automate AMA!

Join Priya Kodukula and the licensing team, super users and MVPs to find answers to your questions on Power Automate licensing.

Users online (3,291)