Delay until 3 days before due date

If I have a due date on a SharePoint list, how do send a notice 3 days before that due date as a reminder, and is it best to have it on create or make it a daily schedule?

2 REPLIES 2
eric-cheng
Solution Sage
Solution Sage

Hi @send2mark ,

 

Will the date ever be 30+ days into the future?  There is a limit of 30 days so you may need to use a recurrence / scheduled flow.

 

--------------------------------------------------------------------------
If I have answered your question, please mark my post as a solution
If you have found my response helpful, please give it a thumbs up

Connect on LinkedIn

oh good point, so let's use the schedule. Based on the date and time field within SharePoint, how do I send an alert 3 days prior to that date?

Helpful resources

Announcements
Power Automate News & Announcements

Power Automate News & Announcements

Keep up to date with current events and community announcements in the Power Automate community.

Community Calls Conversations

Community Calls Conversations

A great place where you can stay up to date with community calls and interact with the speakers.

Power Automate Community Blog

Power Automate Community Blog

Check out the latest Community Blog from the community!

Users online (5,159)