Flow getting to BIG?

Hi All,

 

I have build a rather large Flow (3-tier approval system for 8 types with full tracking & tracing and response time measurements) and I start to notice that when I try to edit the flow it is becoming sluggish.. it takes long to open, long to open an action etc....

 

I have some questions:

  1. Are there other, more powerful tools (maybe offline) to edit flows?
  2. Is there a limit to the size & complexity of a Flow
  3. Is there any progress on "stat flow from flow" requirement request... this would allow for smaller flows...

Any feedback is appreciated

 

Regards

Charles

 

1 ACCEPTED SOLUTION

Accepted Solutions
Highlighted
Dual Super User
Dual Super User

Re: Flow getting to BIG?

Hi @Charles-v-D 

 

1. to edit your flows, and have better governance, check out power clarity: https://powerclarity.app/ 

 

2. Not that I know of but try to keep it as simple as possible. There is a limit on time constraints so ensure that the flow will complete the run in 30 days of time. 

 

3. You can create child flows and that are supposed to be in a solution: https://www.youtube.com/watch?v=_FAgOibUbI0 And you can also trigger new flows using the when an http request is received trigger in the other flow and the http action in your main flow. 

 

Hope this Helps!

If this reply has answered your question or solved your issue, please mark this question as answered. Answered questions helps users in the future who may have the same issue or question quickly find a resolution via search. If you liked my response, please consider giving it a thumbs up. THANKS!

View solution in original post

2 REPLIES 2
Highlighted
Dual Super User
Dual Super User

Re: Flow getting to BIG?

Hi @Charles-v-D 

 

1. to edit your flows, and have better governance, check out power clarity: https://powerclarity.app/ 

 

2. Not that I know of but try to keep it as simple as possible. There is a limit on time constraints so ensure that the flow will complete the run in 30 days of time. 

 

3. You can create child flows and that are supposed to be in a solution: https://www.youtube.com/watch?v=_FAgOibUbI0 And you can also trigger new flows using the when an http request is received trigger in the other flow and the http action in your main flow. 

 

Hope this Helps!

If this reply has answered your question or solved your issue, please mark this question as answered. Answered questions helps users in the future who may have the same issue or question quickly find a resolution via search. If you liked my response, please consider giving it a thumbs up. THANKS!

View solution in original post

Highlighted
Advocate II
Advocate II

Re: Flow getting to BIG?

@yashag2255 

 

OMG: child flows... how long have those be around? not long right? This might be the best thing since..since... ever! 🙂

 

will look into PowerClarity also

 

THANK YOU!

Helpful resources

Announcements
firstImage

Power Platform 2020 release wave 2 plan

Features releasing from October 2020 through March 2021

firstImage

Join the new Power Virtual Agents Community!

We are excited to announce the launch of Power Virtual Agents Community. Check it out now!

firstImage

New & Improved Power Automate Community Cookbook

We've updated and improved the layout and uploading format of the Power Automate Cookbook!

thirdimage

Power Automate Community User Group Member Badge

Fill out a quick form to claim your user group badge now!

Top Solution Authors
Users online (8,686)