Flow getting to BIG?

Hi All,

 

I have build a rather large Flow (3-tier approval system for 8 types with full tracking & tracing and response time measurements) and I start to notice that when I try to edit the flow it is becoming sluggish.. it takes long to open, long to open an action etc....

 

I have some questions:

  1. Are there other, more powerful tools (maybe offline) to edit flows?
  2. Is there a limit to the size & complexity of a Flow
  3. Is there any progress on "stat flow from flow" requirement request... this would allow for smaller flows...

Any feedback is appreciated

 

Regards

Charles

 

1 ACCEPTED SOLUTION

Accepted Solutions
yashag2255
Dual Super User II
Dual Super User II

Hi @Charles-v-D 

 

1. to edit your flows, and have better governance, check out power clarity: https://powerclarity.app/ 

 

2. Not that I know of but try to keep it as simple as possible. There is a limit on time constraints so ensure that the flow will complete the run in 30 days of time. 

 

3. You can create child flows and that are supposed to be in a solution: https://www.youtube.com/watch?v=_FAgOibUbI0 And you can also trigger new flows using the when an http request is received trigger in the other flow and the http action in your main flow. 

 

Hope this Helps!

If this reply has answered your question or solved your issue, please mark this question as answered. Answered questions helps users in the future who may have the same issue or question quickly find a resolution via search. If you liked my response, please consider giving it a thumbs up. THANKS!

View solution in original post

2 REPLIES 2
yashag2255
Dual Super User II
Dual Super User II

Hi @Charles-v-D 

 

1. to edit your flows, and have better governance, check out power clarity: https://powerclarity.app/ 

 

2. Not that I know of but try to keep it as simple as possible. There is a limit on time constraints so ensure that the flow will complete the run in 30 days of time. 

 

3. You can create child flows and that are supposed to be in a solution: https://www.youtube.com/watch?v=_FAgOibUbI0 And you can also trigger new flows using the when an http request is received trigger in the other flow and the http action in your main flow. 

 

Hope this Helps!

If this reply has answered your question or solved your issue, please mark this question as answered. Answered questions helps users in the future who may have the same issue or question quickly find a resolution via search. If you liked my response, please consider giving it a thumbs up. THANKS!

View solution in original post

@yashag2255 

 

OMG: child flows... how long have those be around? not long right? This might be the best thing since..since... ever! 🙂

 

will look into PowerClarity also

 

THANK YOU!

Helpful resources

Announcements
Process Advisor

Introducing Process Advisor

Check out the new Process Advisor community forum board!

MPA User Group

Welcome to the User Group Public Preview

Check out new user group experience and if you are a leader please create your group

MBAS on Demand

Microsoft Business Applications Summit sessions

On-demand access to all the great content presented by the product teams and community members! #MSBizAppsSummit #CommunityRocks

Users online (17,310)