Flow with Outlook and Planner

Hi,

 

I have set up a flow to create a planner task within a teams chanell when an outlook email is flagged. I have a few questions on how to improve this flow.

 

I am wondering is it possible to have the email as an attachment in the planner task, or even just bring more information on the email as it just gets the email subject.

Can the follow up date that is set within outlook be the due date for the planner task?

Also would it be possible to have a pre defined workflow for the planner tasks? For example a set number of tasks that need to be completed for every task.

 

Apprectiate any feedback!

 

Thanks

2 REPLIES 2
Community Support Team
Community Support Team

Re: Flow with Outlook and Planner

Hi @Conor96 ,

 

There is no any way to have the email as an attachment in the planner task, if you want to bring more information on the email, you could send the email body to the task description as screenshot below:

1.png 

 

Could you please explain more details about the "Can the follow up date that is set within outlook be the due date for the planner task?Also would it be possible to have a pre defined workflow for the planner tasks? For example a set number of tasks that need to be completed for every task." that you mentioned?

 

Best regards,

Alice       

Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Conor96
Level: Powered On

Re: Flow with Outlook and Planner

Hi Alice,

 

Thanks for the reply!

 

So within outlook this option is available. When you select follow up you can set a due date. The flow then runs and creates the planner task however the due date entered here does not go to the planner task. Would it be possible to have the due date set here to be the due date for the task?

Forum.JPG

 

 

 

On the predefined workflow, is it possible that when an email is flagged and the planner task is created that a set of sub tasks can be added to the task in the checklist field? So in the below example could this checklist be automatically added to all the planner tasks that are created from the flagged email?

Forum1.JPG

 

 

Thanks for your help!

 

Conor

 

Helpful resources

Announcements
firstImage

Better Together Contest Finalists Announced!

Congrats to the finalists of our ‘Better Together’-themed T-shirt design contest! Click for the top entries.

firstImage

Incoming: New and improved badges!

Look out for new contribution recognition badges coming SOON!

firstImage

New & Improved Power Automate Community Cookbook

We've updated and improved the layout and uploading format of the Power Automate Cookbook!

thirdimage

Power Automate Community User Group Member Badge

Fill out a quick form to claim your user group badge now!

sixthImage

Community Summit North America

The top training and networking event across the globe for Microsoft Business Applications

Top Solution Authors
Top Kudoed Authors
Users online (8,931)