I want to get the members currently assigned to shift from Teams shift.
I specified startTime and endTime for ListShifts as shown, but all shifts are returned.
Is this a bug?
Solved! Go to Solution.
Hi @ncoota ,
I have made a test on my side and the issue is confirmed on my side, the 'From Start Time' and 'To End Time' was ignored on the "Shifts: List all team shifts" action.
I have posted this issue to my product team, if the issue is solved, I will reply here.
Best regards,
Alice
Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi @ncoota ,
Could you please share a screenshot of all the team shifts?
Could you please share the return data from the "List all team shifts" action in your flow?
Also please make sure the start time and end time are in utc format.
Best regards,
Alice
Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi, @v-alzhan-msft,
> Could you please share a screenshot of all the team shifts?
There is a slight shift before October, but only this October.
> Could you please share the return data from the "List all team shifts" action in your flow?
I will post it later because it will be quite large.
It seems that only 100 cases are returned at most. . .
> Also please make sure the start time and end time are in utc format.
"start" and "end" use getFutureTime and addHours method respectively as shown below and are in UTC.
For reference, the following is also the Flow Run history that was executed at 12:39 JST.
The response of “List all team shifts” is as follow link.
Password: T225XmQi6qPF
Same here!
The filter for start and end date in flow is not being applied:
I am having almost the exact same problem. I have tried getting two weeks previous to a month ahead, now to a month ahead and no date/time at all and all I get is the shifts for the whole of July July. It would be useful if it was three months ago.
After re-reading ncoota's post I thought maybe I had over 100 rows being returned and I was hitting a 100 row ceiling but my results are 84 rows so that is not it.
Hi @ncoota ,
I have made a test on my side and the issue is confirmed on my side, the 'From Start Time' and 'To End Time' was ignored on the "Shifts: List all team shifts" action.
I have posted this issue to my product team, if the issue is solved, I will reply here.
Best regards,
Alice
Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi, @v-alzhan-msft and all
Thank you for comment.
By the way, I set this topic to "Resolved", but it's a mistake. Can I cancel it?
Is this issue still un-resolved?
Dive into the Power Platform stack with hands-on sessions and labs, virtually delivered to you by experts and community leaders.