cancel
Showing results for 
Search instead for 
Did you mean: 
Reply
Highlighted
Memorable Member
Memorable Member

Message after updated flow in Japanese. "[完了]5D; を"

I hope to delete "5D;" in a message after updated flow in Japanese.

Or replace "▷"

1.png

 

 

 

 

 

The message:

"フローを更新しました。終了するには、[完了]5D; をクリックしてください。"

 

The string "5D;" does not need.

 

Repro step

1. Edit flow. "フローの編集"

2. Update flow. "フローの更新"

3. Check the message before "▷ 完了"

 

Regards,

Yoshihiro Kawabata

1 ACCEPTED SOLUTION

Accepted Solutions
Highlighted
Power Automate
Power Automate

Re: Message after updated flow in Japanese. "[完了]5D; を"

@yoshihirok Could you try again and see if it is fixed on the new header. Let us know if you are still facing with the issue.

View solution in original post

6 REPLIES 6
Highlighted
Microsoft
Microsoft

Re: Message after updated flow in Japanese. "[完了]5D; を"

Hi Kawabata san

 

フィードバックをお送りいただきありがとうございます。

これは、Microsoft のエンジニアリング チームが現在調査中の既知の問題です。 

引き続きお客様の貴重なフィードバックをお寄せください。

よろしくお願いいたします。

 

Thank you for the feedback. This is a known issue and we are currently fixing it. 

We will keep you updated when the issue is resolved. 

 

Regards

Elsa

 

Highlighted
Memorable Member
Memorable Member

Re: Message after updated flow in Japanese. "[完了]5D; を"

Thank you @elsasung for fixing it.

 

and I am waiting for fix it

 

Regards,

Yoshihiro Kawabata

Highlighted
Memorable Member
Memorable Member

Re: Message after updated flow in Japanese. "[完了]5D; を"

I' waiting to fixing this issue "[完了]5D;" .

 

"x-ms-build-version":"1.0.2244.6.fa49700 Flow-Service.release_20170728 (CY1AZRBLDVM227.170801-1118)"

 

1.png

 

Regards,

Yoshihiro Kawabata

 

Highlighted
Microsoft
Microsoft

Re: Message after updated flow in Japanese. "[完了]5D; を"

Thank you Kawabata. This is a known issue and our engineering team is trying to fix it. 

 

@RajRa Would you please take care of this issue? Thank you.

 

Regards,

Elsa 

Flow international team.

Highlighted
Power Automate
Power Automate

Re: Message after updated flow in Japanese. "[完了]5D; を"

@yoshihirok Could you try again and see if it is fixed on the new header. Let us know if you are still facing with the issue.

View solution in original post

Highlighted
Memorable Member
Memorable Member

Re: Message after updated flow in Japanese. "[完了]5D; を"

Fixed @prabir

I can not found this issue.

Next time, I will report step-by-step for re-produce this issue.

Helpful resources

Announcements
Upcoming Events

Experience what’s next for Power Automate

See the latest Power Automate innovations, updates, and demos from the Microsoft Business Applications Launch Event.

Community Conference

Power Platform Community Conference

Find your favorite faces from the community presenting at the Power Platform Community Conference!

FirstImage

Microsoft Ignite 2020

Check out the announcement of Power Platform content at Microsoft Ignite!

firstImage

Power Platform 2020 release wave 2 plan

Features releasing from October 2020 through March 2021

Users online (12,301)