I have a flow which creates a Planner task from OneNote "Outlook Tasks" option.  But when this Planner task gets completed I would like to update the Todo to show completed too.

 

How is that done? The IDs appear to be different, and I don't know how to look for a Todo task that matches the Planner task.

Thank you

Screenshot 2022-03-25 124818.jpg

 

1 ACCEPTED SOLUTION

Accepted Solutions
RedCoatinOhio1
New Member

Thank you Johnny! You got me a lot further to the goal..My company won't allow me access to the Outlook integration, so I used the Todo instead with this. It seems to work! I'm shocked 😀

Screenshot 2022-03-27 162422.jpg

View solution in original post

2 REPLIES 2
Johnnyg
Community Support
Community Support

Hi Red,

Please check below known solution>
https://powerusers.microsoft.com/t5/Building-Flows/Getting-a-Outlook-task-ID-based-on-Planner-title-... 

Best Regards,
Johnny
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
RedCoatinOhio1
New Member

Thank you Johnny! You got me a lot further to the goal..My company won't allow me access to the Outlook integration, so I used the Todo instead with this. It seems to work! I'm shocked 😀

Screenshot 2022-03-27 162422.jpg

Helpful resources

Announcements
Power Automate News & Announcements

Power Automate News & Announcements

Keep up to date with current events and community announcements in the Power Automate community.

Community Calls Conversations

Community Calls Conversations

A great place where you can stay up to date with community calls and interact with the speakers.

Power Automate Community Blog

Power Automate Community Blog

Check out the latest Community Blog from the community!

Users online (5,888)