Need Help with Approval Flow - Assigned To vs Requestor & Task Completion

 

Hi - 

 

I have a pretty basics question for the team. I'm using the template below and am confused about the assigned to and requestor fields.

 

My original assumption is that the "Assigned To" field is the user who would receive the request for approval and that the "Requestor Field" is based on who was originally assigned the task. However, I think at least part of that assumption is correct. Can anyone clarify the meaning of both fields?

 

Also, depending on what each mean can anyone let me know how I would design a flow that works as desired (i.e. upon completion of a given task within a bucket/plan by user 1, user 2 would receive the approval request? 

 

 

Approval Request Flow.PNG

  

I know these are all basic questions but I can't seem to find a glossary of what certain fields mean/function as. 

 

Thanks for the help!

Heather

2 ACCEPTED SOLUTIONS

Accepted Solutions
RobElliott
Super User
Super User

Hi Heather @HParker the Assigned to field is the person who will do the approval or rejection. The Requestor is the person who is requesting the approval. In your scenario that will be the person who completed the task in Planner and you'd select value assignments Assigned To User Id from the dynamic content for that field in the flow.

Rob
Los Gallardos
If I've answered your question or solved your problem, please mark this question as answered. This helps others who have the same question find a solution quickly via the forum search. If you liked my response, please consider giving it a thumbs up. Thanks.

 

 

View solution in original post

v-alzhan-msft
Community Support
Community Support

Hi @HParker ,

 

You should compare the Outcome dynamic content with Approve in the Condition.

 

Best regards,
Alice       
 
Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

2 REPLIES 2
RobElliott
Super User
Super User

Hi Heather @HParker the Assigned to field is the person who will do the approval or rejection. The Requestor is the person who is requesting the approval. In your scenario that will be the person who completed the task in Planner and you'd select value assignments Assigned To User Id from the dynamic content for that field in the flow.

Rob
Los Gallardos
If I've answered your question or solved your problem, please mark this question as answered. This helps others who have the same question find a solution quickly via the forum search. If you liked my response, please consider giving it a thumbs up. Thanks.

 

 

View solution in original post

v-alzhan-msft
Community Support
Community Support

Hi @HParker ,

 

You should compare the Outcome dynamic content with Approve in the Condition.

 

Best regards,
Alice       
 
Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

Helpful resources

Announcements
MPA User Group

Welcome to the User Group Public Preview

Check out new user group experience and if you are a leader please create your group

MBAS on Demand

Microsoft Business Applications Summit sessions

On-demand access to all the great content presented by the product teams and community members! #MSBizAppsSummit #CommunityRocks

MBAS Attendee Badge

Claim Your Badge & Digital Swag!

Check out how to claim yours today!

secondImage

Are Your Ready?

Test your skills now with the Cloud Skill Challenge.

Top Solution Authors
Users online (70,157)