Hi,

 

I am in the process of building a flow that looks at the number of Km/s a vehicle is at and if the number reaches a certain number then a new item is created and the vehicle is booked into a work order list,

 

For eg see below

 

forUM!!!.png

 

This is the only way i have figured out how to do?

 

Currently its set to greater than 200 and less than 250 and then i have to create a second flow of between 450 and 500 and then 700 and 750 etc etc,

 

Without creating hundreds of flows is there another way?

 

Thankyou

1 ACCEPTED SOLUTION

Accepted Solutions
Super User II
Super User II

You can create parallel branches, example: FormsCreateTaskParallelBucket.PNGYou can add a parallel branch by clicking the Plus sign between steps (red box) and selecting Add parallel branch (green box): AddParallelBranch.png

If this reply has answered your question or solved your issue, please mark this question as answered. Answered questions helps users in the future who may have the same issue or question quickly find a resolution via search. If you liked my response, please consider giving it a thumbs up. THANKS!

View solution in original post

2 REPLIES 2
Super User II
Super User II

You can create parallel branches, example: FormsCreateTaskParallelBucket.PNGYou can add a parallel branch by clicking the Plus sign between steps (red box) and selecting Add parallel branch (green box): AddParallelBranch.png

If this reply has answered your question or solved your issue, please mark this question as answered. Answered questions helps users in the future who may have the same issue or question quickly find a resolution via search. If you liked my response, please consider giving it a thumbs up. THANKS!

View solution in original post

Community Support
Community Support

Hi @shaneOZ ,

 

Using parallel branches is a possible way to achieve your scenario.

 

For more details about adding parallel branches in flows, please check the following doc:

https://flow.microsoft.com/en-us/blog/parallel-actions/

 

Best regards,

Mabel

 

Community Support Team _ Mabel Mao
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
PP Bootcamp Carousel

Global Power Platform Bootcamp

Dive into the Power Platform stack with hands-on sessions and labs, virtually delivered to you by experts and community leaders.

secondImage

Power Platform Community Conference On Demand

Watch Nick Doelman's session from the 2020 Power Platform Community Conference on demand!

MPA Community Blog

Power Automate Community Blog

Check out the community blog page where you can find valuable learning material from community and product team members!

Top Solution Authors
Users online (3,610)